Project
Project Objective
Based on the success of 24x7 water supply Demonstration Project, the proposal of up-scaling 24x7 water supply to the entire corporation areas of Hubballi-Dharwad, Belagavi, Kalaburagi and at an estimated cost of Rs. 1809.00 Crores has been approved, vide Govt. Order No. UDD 244 PRJ 2013, dated 7.11.2013. The share of the World Bank is 67% (Rs. 1209.00 Crores).
Project Implementation
Kuidfc, which manages a range of urban infrastructure development projects for the gok, will manage project implementation on behalf of the project cities. It has established a pmu which will be responsible for the day-to-day project management, progress monitoring and reporting, procurement activities, and financial management.
Kuidfc has established piu in each project city, which will oversee the day-to-day activities of the project at the city level and will report to the pmu and to the ulb.
An empowered committee has been established to take decisions for implementing the projects
Project
Project Progress
The projects of upscaling of existing intermittent supply to 24x7 Water supply for the three cities of Hubballi-Dharwad , Belagavi, Kalaburagi and are now proposed to be implemented on ‘Design-Build-Operate-Transfer (DBOT)’ with following period:
- Design & Implementation Period – 5 years
- Operation & Management Period – 7 years
The Government has approved the above proposal vide GO No: UDD 279 PRJ 2018, Dated: 22.10.2018. The DBOT contract has been awarded to M/s Larsen & Toubro Chennai and the agreement has been signed on 12.06.2020
ESHS MSIP_Hubli Dharwad_Final_Rev-05_20.11.2023 | |||||
ESHS MSIP_Hubli Dharwad_Final_Rev-05_20.11.2023 (3).pdf. | |||||
HDW- Consumer perception-Final Survey Report .pdf". | |||||
Project Photos .pdf". |
Status of KUWSMP CAPEX Works As on March 2025 | |||
Sl No | Details of Civil work | Quantity | Progress |
---|---|---|---|
1 | 1219 RWTM work from Savadatti Jackwell to Amminbhavi WTP | 29.51 KM | 29.51 KM |
2 | Amminbhavi WTP and other related work | 43 MLD Water Treatment Plant | Civil works completed & Electromechanical works in progress |
3 | CWTM works from Amminbhavi WTP | 75 KM | 61.03 KM |
4 | CWDN (Distribution) | 1688 KM | 618 KM |
5 | GLSR & ELSR construction works | 23 No's | • Out of 14 proposed ELSRs 10 ELSR civil works completed, 3 ELSRs works are under progress & 1 ELSR land purchase is in progress.
• Out of 9 proposed GLSRs 8 GLSRs civil works completed, 1 GLSR work is under progress |
6 | Customer Service Center (CSC) | 8 No's | 6 centers are working (2 Centers civil work under progress) |
7 | Centralized Control Center (CCC) | 1 | 1 center is working |
8 | Community Liaison Cell (CLC) | 1 | 1 center is working |